Friday progress

I was worried today was going to be another bust do to rain however the rain stopped at 7am and it quickly turned into a sunny day!

Today they got the back wall sided all the way up and then primed the soffit and casings/frieze board.

Siding done (the one missing piece is waiting for the window caps to go up).

The plan next week is as follows:

Monday – paint the trim that’s primed, prime the siding, paint the siding (primer dries in 2 hours).

Start the panels on the cupola.

Move the pump station over to the bumpout, get the window caps on, replace the missing shakes and get that peak scraped down.

The attic windows are supposed to arrive mid next week, it looks like they should be here before they really hold up any work which is great.  The back part of the house will be completely done.

My plan this weekend is to strip the base piece so they can paint that along with the rest of the trim (I may prime it so it’s ready to just paint).  I also need to paint the bed molding so they can get that installed before moving the pump station.  Can’t wait to come home monday and see the progress!

One Comment

  1. Everything is suddenly moving along so quickly- it’s fabulous! Imagine what it would be like if the crew had a week of great weather.