Monday progress

Tuesday got rained out again but Monday the rain held off so they were able to get our bedroom windows all installed and a good start on scraping down the soffit over the backside.

Soffit scraping started, coming along nicely

Back side of cupola window progress

Front side – looks good!

Bedroom windows from the inside. They did a good job removing the trim and not really messing with the plaster. This is good because it may be a while before we get to renovating our bedroom.

Now the inside work is done, they are starting on panels on the bumpout today.  At the pace they are going i’d say they may get all the panels on the bumpout done, maybe not the window cap only because it’s tricky?  I’ve got some molding to paint tonight (I want the bed molding to be red and it’s easier if it’s pre-painted).  Everything else will be yellow so it’s up to them when they add the molding, they could do it after painting the rest if they want, I just want to make sure I’m not holding them up.